Example Asbestos Removal Projects in Santa Monica

Here are seven example jobs in Santa Monica, Beverly Hills and Malibu, from a duplex teardown to an office suite floor. Each one lists what was sampled, what came out, the work days and an estimated cost.

Ceilings, floors and pipe wrap removed from a 1930s duplex before it comes down

Example project

Home
1930s duplex in Santa Monica, two units of about 650 sq ft each, with textured ceilings, kitchen linoleum and a crawl space
Original request
Take the duplex down and build a new two-unit building on the lot
Testing
A whole-building survey by a Cal/OSHA-certified asbestos consultant, about 30 samples from both units and the crawl space
Found
Asbestos in the ceiling texture, the kitchen linoleum with its glue and the wrap on the water pipes under the floor
Clear
The wall plaster and the window putty
Area
About 900 sq ft of ceiling, 400 sq ft of floor and 90 ft of pipe wrap
Timeline
Notice no later than 10 working days ahead, then five working days before the wrecking crew
Cost
$24,500

Scope of work

Removal of every material the survey marked positive, the district notice, each unit sealed in turn, wet removal into labeled bags, air monitoring and the haul with its paperwork. The survey, the clearance air test, the demolition and the permits are separate.

Project overview

In this example, an owner is replacing a 1930s duplex with a new building. Santa Monica collects the Rule 1403 notification form and an asbestos report when it issues the demolition permit, so the survey and the district notice are finished before the permit comes through.

The ceilings, the linoleum and the pipe wrap test positive, and the plaster is clear. The abatement crew takes out the three materials first, and the wrecking crew starts afterward.

The goal

The goal is a duplex with every positive material gone, so the wrecking crew starts the day the permit allows.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples both units and the crawl space and writes the report.
  2. Before work The abatement contractor files the district notice online, and the form and report wait for permit issuance.
  3. Days one to five Each unit is sealed, the ceilings and linoleum come out wet, and the pipe wrap is removed under the floor.
  4. Last An independent consultant tests the air, then the wrecking crew starts.

Planning right

  • Order the survey as soon as the owner decides to rebuild.
  • Keep the report and the notice form together for permit day.
  • Ask the wrecking crew to hold its date until the air results are in.
  • Plan truck access to the alley or street side.

Get a free quoteMore about renovation and demolition abatement

Kitchen and hall floor lifted in a 1960s apartment before the next lease

Example project

Building
1960s apartment building in Santa Monica, a one-bedroom unit with worn vinyl in the kitchen and hall
Original request
Replace the kitchen and hall floor after the tenant moves out
Testing
A Cal/OSHA-certified asbestos consultant samples the vinyl, the 9-inch tile under it and the black glue
Found
Asbestos in the 9-inch tile and the glue
Clear
The vinyl on top
Area
About 280 sq ft of kitchen and hall floor
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$3,800

Scope of work

Lab results for each layer, the district notice, the unit sealed with air filters running, the vinyl lifted and the tile and glue taken up wet to the slab, bagged disposal and a cleanup. The clearance air test and the new floor are separate.

Project overview

In this example, the owner of a 1960s apartment building is turning over a second-floor unit. The vinyl has peeled at the kitchen door, and an older tile shows under it.

An apartment is never a single-unit dwelling, so the survey is part of the job whatever the size, and the district notice is filed unless the removal stays under 100 square feet. The tile and glue test positive, and the abatement crew finishes before the flooring installer is booked.

The goal

The goal is a bare slab in the unit, so the next tenant moves in on a new floor with nothing positive beneath it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant lifts a corner of the vinyl and samples every layer.
  2. Before work The abatement contractor files the district notice online.
  3. Day one The unit is sealed, the vinyl comes up and the tile is lifted by hand.
  4. Day two The glue is removed wet, the slab is cleaned and an independent consultant tests the air.

Planning right

  • Tell the neighbors below and beside the unit when the work days are.
  • Book the flooring installer after the air results.
  • Ask the consultant to sample the bathroom floor while the unit is empty.
  • File the report in the building binder under the unit number.

Get a free quoteMore about floor tile and mastic removal

Whole-house survey ahead of a demolition permit for a 1940s house

Example project

Home
1940s house in Beverly Hills of about 2,300 sq ft, with plaster ceilings, a tile kitchen floor and a furnace with wrapped ducts
Original request
Demolish the house and build a new one
Testing
A Cal/OSHA Certified Asbestos Consultant samples ceilings, walls, floors, window glazing and the duct wrap, about 20 samples in all
Found
Asbestos in the kitchen floor tile and glue and in the duct wrap
Clear
The plaster, the window glazing and the roof felt
Timeline
The signed survey comes first, then the demolition permit, then removal is scheduled
Estimated testing cost
$1,100

Scope of work

A visit by the consultant, about 20 samples, a lab result for each and a written report that says asbestos is present and where. Removal, the clearance air test and the demolition are priced separately.

Project overview

In this example, a family is replacing a 1940s house in Beverly Hills. The city asks for a survey by a Cal/OSHA Certified Asbestos Consultant stating whether asbestos is present before it issues the demolition permit.

The report finds asbestos in two places, so a copy of the district notice goes to the building department before the permit is issued. The abatement crew removes the tile and the duct wrap, and the demolition follows.

The goal

The goal is a signed survey in hand, so the demolition permit and the removal both move on the same plan.

Process

  1. First visit A Cal/OSHA Certified Asbestos Consultant samples every room, the ducts and the glazing.
  2. Report The consultant signs a survey that says asbestos is present and lists the two materials.
  3. Before work The abatement contractor files the district notice online, and a copy goes to the building department.
  4. Then The abatement crew removes the tile and the duct wrap, and the demolition is scheduled.

Planning right

  • Ask for the report as a signed PDF as well as a paper copy.
  • Do not take samples yourself, the consultant knows what to cut.
  • Hold the demolition crew until the notice is filed.
  • Keep the report with the permit set.

Get a free quoteMore about asbestos testing and surveys

Wall compound removed from the standing walls of a fire-damaged house

Example project

Home
1970s single-story house in Malibu, burned on one side, with the bedroom wing walls still standing
Original request
Clear the lot so the family can rebuild
Testing
A Certified Asbestos Consultant surveys the standing walls, the remaining ceilings and the floors before any cleanup
Found
Asbestos in the joint compound on the standing bedroom-wing walls
Clear
The remaining ceilings and the slab
Area
About 420 sq ft of wall
Timeline
Notice no later than 10 working days ahead, then three working days before the debris crew
Cost
$5,800

Scope of work

The standing wing sealed with air filters running, wet removal of the positive wall compound, bagged disposal and a cleanup. The survey, the debris and ash removal, the clearance air test and the rebuild are separate.

Project overview

In this example, a family in Malibu is rebuilding after a fire took one side of the house. The city’s fire page lists the asbestos survey as the first phase of debris removal, ahead of the debris and ash.

The district’s rule still applies to a fire-damaged building and its debris. The wall compound tests positive, so the abatement crew takes it out before the debris crew works near the wing.

The goal

The goal is standing walls with the positive compound gone, so the debris crew works without disturbing it.

Process

  1. First visit A Certified Asbestos Consultant samples the standing walls, ceilings and floors.
  2. Before work The abatement contractor files the district notice online.
  3. Days one to three The wing is sealed and the compound is removed wet, then bagged and hauled.
  4. Last An independent consultant tests the air, and the debris crew starts.

Planning right

  • Ask the consultant to number the standing walls on a sketch.
  • Share the insurance scope with the consultant so every wall is covered.
  • Ask the debris crew to wait for the air results.
  • Keep the report with the rebuild permit papers.

Get a free quoteMore about drywall, joint compound and plaster removal

Kitchen ceiling texture removed in a condo before new cabinets go in

Example project

Home
1970s condominium in Santa Monica, third floor, with a textured ceiling over the kitchen and dining area
Original request
Replace the upper cabinets and take the soffit down, which damages the ceiling
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture at three spots
Found
Asbestos in the ceiling texture
Area
About 170 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$2,000

Scope of work

Samples and lab results, the district notice, the kitchen and dining area sealed with air filters running, the texture wetted and scraped into bags, a HEPA clean and the haul. The clearance air test, the cabinets and the new finish are separate.

Project overview

In this example, a condo owner is replacing the upper cabinets, and taking down the soffit will tear the textured ceiling above. A condominium is not a single-unit dwelling, so the survey applies, and so does the district notice unless the removal stays under 100 square feet.

The texture tests positive. The abatement crew removes it from the whole kitchen and dining ceiling, and the cabinet installer works under a bare ceiling.

The goal

The goal is a bare ceiling, so the new cabinets and lighting go in with nothing positive above them.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceiling in three places.
  2. Before work The abatement contractor files the district notice online, and the owner tells the building manager the work dates.
  3. Day one The area is sealed and the texture is wetted and scraped.
  4. Day two The ceiling is wiped, the bags go out through the freight route and an independent consultant tests the air.

Planning right

  • Ask the building manager about elevator and loading rules.
  • Take small items and art off the kitchen walls.
  • Order the cabinets for a date after the air results.
  • Give the association a copy of the report.

Get a free quoteMore about popcorn ceiling removal

Pipe wrap removed from a stairwell chase opened after a leak

Example project

Building
1960s courtyard apartment building in Santa Monica with open stairwells and pipe chases behind the stairwell walls
Original request
Repair a leaking supply line inside the chase and patch the stairwell wall
Testing
A Cal/OSHA-certified asbestos consultant samples the pipe wrap at four spots and the plaster around the leak
Found
Asbestos in the pipe wrap
Clear
The stairwell plaster
Area
About 45 ft of wrapped pipe in the chase
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$2,300

Scope of work

A sealed work area at the stairwell, the chase opened, the positive wrap removed wet, bagged disposal and a cleanup. The survey, the plumbing repair, the clearance air test and the wall patch are separate.

Project overview

In this example, a leak shows up on the wall of a stairwell in a courtyard building, and the plumber needs to open the pipe chase behind it. The old pipes are wrapped, so the wrap is sampled before the wall is cut.

The wrap tests positive and the plaster is clear. The abatement crew removes the wrap, and the plumber repairs the line afterward.

The goal

The goal is a pipe chase with the old wrap gone, so the plumber works on bare pipe.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap and the plaster, then the plumber waits.
  2. Before work The abatement contractor files the district notice online, and the manager posts the work dates for residents.
  3. Day one The stairwell section is sealed, the chase is opened and the wrap is removed wet.
  4. Day two The chase is cleaned and an independent consultant tests the air, then the plumber starts.

Planning right

  • Post a notice at the stairwell entrance for the work days.
  • Keep the water shutoff plan with the plumber.
  • Ask the consultant to mark every sampled spot on a sketch of the chase.
  • Patch the wall only after the air results.

Get a free quoteMore about HVAC duct and pipe insulation removal

Floor tile and glue removed from a ground-floor office suite before a lease change

Example project

Building
1960s two-story office building in Santa Monica, a ground-floor suite of about 1,150 sq ft
Original request
Strip the suite to the slab for the next tenant’s new floor
Testing
A Cal/OSHA-certified asbestos consultant samples the floor tile, the glue, the carpet backing and the ceiling tiles
Found
Asbestos in the 9-inch floor tile and its glue
Clear
The carpet backing and the ceiling tiles
Area
About 1,150 sq ft of floor
Timeline
Notice no later than 10 working days ahead, then four working days
Cost
$9,800

Scope of work

The suite sealed with air filters running, carpet and tile removed, the glue taken up wet where it tested positive, disposal records and a cleanup. The survey, the district notification fee, the clearance air test and the new floor are separate.

Project overview

In this example, a landlord is preparing a ground-floor suite for a new tenant who wants polished concrete. The carpet comes up easily, and the old tile and glue sit beneath it.

The suite is a commercial space, so the survey applies in full, and so does the district notice unless the removal stays under 100 square feet. The tile and glue test positive, and the abatement crew finishes before the next tenant’s contractor starts.

The goal

The goal is a bare slab, so the new tenant starts the finish work on clean concrete.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the floor layers and the ceiling tiles.
  2. Before work The abatement contractor files the district notice online.
  3. Days one to three The suite is sealed, the carpet is lifted off and the tile and glue are removed.
  4. Day four The slab is cleaned and an independent consultant tests the air.

Planning right

  • Move the old tenant’s furniture out before work begins.
  • Tell the other suites on the floor the work dates.
  • Give the new tenant’s contractor the report and the air results.
  • Schedule the concrete polishing after the air results.

Get a free quoteMore about apartments, condos and commercial suites

Request a free asbestos removal quote