Ceilings, floors and pipe wrap removed from a 1930s duplex before it comes down
Example project
- Home
- 1930s duplex in Santa Monica, two units of about 650 sq ft each, with textured ceilings, kitchen linoleum and a crawl space
- Original request
- Take the duplex down and build a new two-unit building on the lot
- Testing
- A whole-building survey by a Cal/OSHA-certified asbestos consultant, about 30 samples from both units and the crawl space
- Found
- Asbestos in the ceiling texture, the kitchen linoleum with its glue and the wrap on the water pipes under the floor
- Clear
- The wall plaster and the window putty
- Area
- About 900 sq ft of ceiling, 400 sq ft of floor and 90 ft of pipe wrap
- Timeline
- Notice no later than 10 working days ahead, then five working days before the wrecking crew
- Cost
- $24,500
Scope of work
Removal of every material the survey marked positive, the district notice, each unit sealed in turn, wet removal into labeled bags, air monitoring and the haul with its paperwork. The survey, the clearance air test, the demolition and the permits are separate.
Project overview
In this example, an owner is replacing a 1930s duplex with a new building. Santa Monica collects the Rule 1403 notification form and an asbestos report when it issues the demolition permit, so the survey and the district notice are finished before the permit comes through.
The ceilings, the linoleum and the pipe wrap test positive, and the plaster is clear. The abatement crew takes out the three materials first, and the wrecking crew starts afterward.
The goal
The goal is a duplex with every positive material gone, so the wrecking crew starts the day the permit allows.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples both units and the crawl space and writes the report.
- Before work The abatement contractor files the district notice online, and the form and report wait for permit issuance.
- Days one to five Each unit is sealed, the ceilings and linoleum come out wet, and the pipe wrap is removed under the floor.
- Last An independent consultant tests the air, then the wrecking crew starts.
Planning right
- Order the survey as soon as the owner decides to rebuild.
- Keep the report and the notice form together for permit day.
- Ask the wrecking crew to hold its date until the air results are in.
- Plan truck access to the alley or street side.