Wall compound removed from the standing walls of a fire-damaged house
Example project
- Home
- 1970s single-story house in Malibu, burned on one side, with the bedroom wing walls still standing
- Original request
- Clear the lot so the family can rebuild
- Testing
- A Certified Asbestos Consultant surveys the standing walls, the remaining ceilings and the floors before any cleanup
- Found
- Asbestos in the joint compound on the standing bedroom-wing walls
- Clear
- The remaining ceilings and the slab
- Area
- About 420 sq ft of wall
- Timeline
- Notice no later than 10 working days ahead, then three working days before the debris crew
- Cost
- $5,800
In this example, a family in Malibu is rebuilding after a fire took one side of the house. The city’s fire page lists the asbestos survey as the first phase of debris removal, ahead of the debris and ash.